Tube City Community Media Inc. is seeking freelance writers to help cover city council, news and feature stories in McKeesport, Duquesne, White Oak and the neighboring communities. High school and college students seeking work experience are encouraged to apply; we are willing to work with students who need credit toward class assignments. Please send cover letter, resume, two writing samples and the name of a reference (an employer, supervisor, teacher, etc. -- not a relative) to tubecitytiger@gmail.com.

To place your ad, email tubecitytiger@gmail.com.
Ads start at $1 per day, minimum seven days.

East McKeesport Will Re-Bid Stormwater Project

By T.J. Martin
The Tube City Almanac
January 18, 2024
Posted in: Announcements

A newly-received state grant prompted the East McKeesport Borough Council to reject a bid for a portion of a storm water project and they will now seek bids for the entire project.

Borough Engineer Laura Branthoover of Glenn Engineering & Associates Ltd. told the council that the borough recently received a $100,000 Small Water and Sewer Grant from the Pennsylvania Department of Community and Economic Development (DCED) for the Ice Plant Hill Project.

The project is designed to address storm water issues on the two-lane roadway by cleaning out some existing drainage pipes and adding additional collection inlets.

Branthoover said the borough already had a $200,000 Local Share Account (LSA) grant financed with state gaming revenue and a $100,000 community development grant also from the state. With those funds, the borough had sought bids for a portion of the project.

With the new funds, however, the borough will seek new bids for the entire project. Thus, Branthoover recommended that the council reject a bid it had received for a portion of the project and the council voted 6-0 to do so with Council President John Ekiert absent.